Sample Factory Acceptance Testing

This functional Factory Acceptance Testing (FAT) Protocol & Live Execution Script builds directly upon the pre-FAT cold check sign-off. It provides a step-by-step procedure for controlled first-time energisation, safety system trip validation under BS EN 60204-1 / BS EN ISO 13849-1, and systematic PLC I/O loop checks.

Factory Acceptance Testing (FAT) Protocol & Live Script

Document Reference: FAT-PROT-[YEAR]-[001]

Panel Reference: [e.g., MCC-L3-001]

Associated SOW: [SOW-Reference-No]

Test Location: [Workshop / Test Bay Name]

Date of Test: [DD/MM/YYYY]

Test Personnel:

  • Lead Electrical Wireman / Commissioning Engineer: [Contractor Representative]
  • Lead Controls / Software Engineer: [Software Engineer Name]
  • Client / Technical Witness: [Client Representative Name]

1. Safety Prerequisites & Pre-Energisation Sign-Off

SAFETY NOTICE: Prior to connecting temporary test supplies, verify that the Pre-FAT Cold Inspection Sheet is signed off, all trunking lids are closed, bare copper is shrouded, and test bay barriers/signage are erected.

  • [ ] Section 1–6 Cold Checks completed and signed off.
  • [ ] Calibration certificates verified for digital multimeter (CAT III/IV) and phase-rotation meter.
  • [ ] Temporary 3-phase/neutral/earth supply isolated, locked out, and tagged out (LOTO).
  • [ ] Fire protection equipment suitable for electrical fires ($CO_2$) within reach.

2. Stage 1: Initial Controlled Energisation Script

┌──────────────────────────────────────────────────────────────────────────────┐
│                    CONTROLLED ENERGISATION SEQUENCE                          │
├──────────────────────────────────────────────────────────────────────────────┤
│ 1. Isolate all branch MCBs/MPCBs/fuses on the chassis.                       │
│ 2. Close main incoming switch-disconnector (door isolator).                  │
│ 3. Prove incoming voltage (L-L, L-N, L-PE) and phase sequence (L1-L2-L3).    │
│ 4. Step-energise auxiliary transformers and 24V DC Switch Mode Power Supply. │
│ 5. Sequentially energise downstream field distribution breakers.             │
└──────────────────────────────────────────────────────────────────────────────┘
StepAction / ProcedureExpected ResultMeasured / ObservedPass / FailInitials
1.1Open all internal outgoing MCBs, MPCBs, and auxiliary fuses. Leave only the main incoming line switch closed.Incoming terminals live; all internal load circuits isolated.Complete isolation confirmed[ ]
1.2Connect supply. Measure incoming supply voltage at main isolator terminals L1-L2, L2-L3, L3-L1.$400\text{V AC} \pm 10\%$ ($360\text{V} – 440\text{V}$) balanced across phases.L1-L2: ______ V

L2-L3: ______ V

L3-L1: ______ V
[ ]
1.3Measure incoming neutral to earth N-PE.$< 5\text{V AC}$ under normal workshop supply conditions.N-PE: ______ V[ ]
1.4Check phase rotation using calibrated meter.Clockwise (standard L1-L2-L3 sequence).Clockwise confirmed[ ]
1.5Close 24V DC Power Supply primary circuit protection.PSU powers up; “DC OK” LED illuminated.Green LED ON[ ]
1.6Measure regulated DC output at main distribution terminals (+24V to 0V).$24.0\text{V DC} \pm 0.4\text{V}$ (range $23.6\text{V} – 24.4\text{V}$).Measured: ______ V[ ]
1.7Measure DC reference rail to earth (0V to PE).Matches grounding philosophy: $0.0\text{V}$ (grounded SELV) or high-impedance floating (PELV).0V-PE: ______ V[ ]

3. Stage 2: Functional Safety Circuits & E-Stop Trip Validation

Tested in accordance with BS EN ISO 13849-1 (PLr architecture) and BS EN 60204-1.

StepSafety Device Under TestTest Method / Operator ActionExpected ReactionObserved ReactionPass / Fail
2.1Safety Relay ResetEnsure all E-Stops released. Press panel door “Safety Reset” pushbutton.Safety Relay energises; safety contactors pull in; channel LEDs illuminate steady green.[ ]
2.2Door Emergency Stop (S1)Depress panel door E-Stop mushroom pushbutton.Instant drop-out of safety relay and dual redundant contactors ($< 50\text{ ms}$). HMI/Beacon indicates “E-Stop Tripped”.[ ]
2.3Safety Relay Anti-Tie-DownHold Reset button pressed while releasing E-Stop S1.Relay MUST NOT automatically reset (fault-lockout mode). Manual re-press required.[ ]
2.4Dual-Channel Cross-Fault CheckDisconnect one channel (Channel A) at safety gate/terminal while relay is active.Safety relay trips immediately; cross-monitoring detects discrepancy; relay inhibits re-energisation.[ ]
2.5Safety Interlock Switches (Door Switches)Actuate guard door magnetic/RFID interlock switch while safety is active.Safety circuit de-energises; auxiliary contact flags open safety guard on PLC input.[ ]
2.6Orange Core Foreign InterlocksTurn main door isolator OFF. Check voltage on designated orange control cores.Interlock terminals remain active (indicated by orange wire and external supply warning label).[ ]

4. Stage 3: PLC I/O Loop Testing & Software Verification

Connect programming terminal via industrial Ethernet/Profinet. Verify individual hardware states against the master engineering I/O list.

Digital Inputs (DI) Verification

Method: Apply local 24V DC test signal / operate field switch sim.

Channel / AddressTerminal RefDescription / Signal NameHardware StatePLC Monitor TagResult
%I0.0X2:1Main Air Pressure Switch OKON / 24V DCDI_AirPress_OK = TRUE[ ]
%I0.1X2:2Cell Safety Guard ClosedON / 24V DCDI_Guard_Closed = TRUE[ ]
%I0.2X2:3Master Start PushbuttonDepressedDI_Master_Start = TRUE[ ]
%I0.3X2:4VFD 1 Fault Healthy ContactSimulate TripDI_VFD1_Trip = TRUE[ ]

Digital Outputs (DO) Verification

Method: Force output through PLC engineering software / HMI manual mode.

Channel / AddressTerminal RefDescription / Signal NameSoftware ForcePhysical ReactionResult
%Q0.0X3:1Beacon Green (Running)FORCE HIGHGreen stack light element illuminated.[ ]
%Q0.1X3:2Beacon Red (Fault/Trip)FORCE HIGHRed element illuminated + sounder pulse.[ ]
%Q0.2X3:3Main Contactor 1 EnableFORCE HIGHContactor coil pulls in; auxiliary closes.[ ]
%Q0.3X3:4Pneumatic Solenoid Dump ValveFORCE HIGH24V DC measured at field connector terminals.[ ]

Analogue I/O Checks (AI / AO)

Method: Calibrated 4–20mA / 0–10V process loop calibrator.

ChannelSignal TypeTest Point0% Input50% Input100% InputLinear Scaled ValueResult
%IW644–20 mAPressure Transducer$4.00\text{ mA}$$12.00\text{ mA}$$20.00\text{ mA}$$0.0 – 10.0\text{ bar}$[ ]
%QW640–10 VVFD Speed Reference$0.00\text{ V}$$5.00\text{ V}$$10.00\text{ V}$$0.0 – 50.0\text{ Hz}$[ ]

5. Live Snagging & Punch-List Log

Item #System / ComponentDefect ObservedRemedial Action RequiredTarget RectificationCleared (Initials)
1[e.g., Beacon Sounder]No audible tone when forcedCheck 0V return on terminal X3:5Pre-dispatch[ ]
2[e.g., MPCB 2 Aux]Aux contact normally open instead of NCSwap terminal connections on blockPre-dispatch[ ]

6. FAT Certification Sign-Off

Conditional Acceptance:

The panel assembly described herein has been tested in accordance with the FAT functional protocol. Subject to the clearance of any minor non-conformances listed in Section 5 above, the panel is certified for dispatch and site delivery.

Lead Commissioning Engineer / Contractor:

Name: ___________________________________

Signature: ________________________________

Date: [DD/MM/YYYY]

Client Witness / Technical Representative:

Name: ___________________________________

Signature: ________________________________

Date: [DD/MM/YYYY]